Crusoe confirmed on Friday that it has sold an unfinished data center project in southeastern Wyoming to Google. Crusoe is an eight-year-old, Denver-based data center developer recently valued at $30.9 billion. Google had been a target customer for the site, and the company is now taking over development itself. According to the reporting, Google raised concerns about the project's cost and the construction timeline under Crusoe's management.

The financial terms were not disclosed. Google did announce plans to invest $17 billion to develop the data center campus. Crusoe first announced the project last year in partnership with Tallgrass, a Blackstone-backed infrastructure company, with an eventual target of scaling to 10 gigawatts of power capacity. For context, a gigawatt is a billion watts, so 10 gigawatts is an enormous figure, comparable to the output of several large power plants. That ambition helps explain why execution risk is so high.

The sale illustrates how hard it is for independent developers to deliver very large data centers on schedule and on budget, given the difficulty of securing equipment and power. Local community opposition can add further friction. This suggests the bottleneck for AI infrastructure is shifting from chip supply toward the physical buildout: land, grid interconnects, turbines, transformers and construction labor. A likely trade-off is that hyperscalers such as Google can absorb cost overruns and negotiate power and equipment at a scale independents cannot, which may push more of these mega-projects under their direct ownership over time.

Google has not walked away from Crusoe entirely. Crusoe is developing another data center for Google near Amarillo, Texas, so the relationship continues even as the Wyoming asset changes hands.

The sale was first reported by Bloomberg in June. The Wyoming setback did not prevent Crusoe from raising a $3.9 billion round in September. Crusoe's business model combines three revenue streams: leasing data center space to customers that bring their own GPUs, renting out its own GPUs, and selling compute used to run AI models, known as inference.

Its largest projects serve prominent AI names. The Abilene, Texas campus is being built in phases for Oracle and OpenAI. Crusoe is also constructing a separate 900-megawatt campus next door for Microsoft, with its first building expected to come online in mid-2027. Meta is also a customer, and Bloomberg reported that trading firm Jane Street signed a $13 billion, five-year cloud deal with Crusoe.

Crusoe was founded by Chase Lochmiller, now CEO, and Cully Cavness. It began as a cryptocurrency-mining business powered by natural gas that would otherwise have been flared off. In September, alongside the funding round, the company added three board members, including JB Straubel, the Redwood Materials founder and Tesla board member who invested in Crusoe in 2021. Crusoe later became the first customer of Straubel's energy-storage business.

Why it matters: Developers and product teams planning around AI capacity should read this as a sign that power and construction, not chips, increasingly gate timelines. Google bringing a large campus in-house suggests hyperscalers may take over stalled builds directly, which could change who controls available compute in a region. For teams relying on third-party capacity, diversify providers and treat delivery dates as uncertain. That last point is inference, but it follows from the execution problems described here.

Read at TechCrunch · AI

Based on reporting from the original publisher. Visit the source for full context and later updates.

Publisher excerpt

The deal highlights the challenges of developing massive AI data centers.