Nebius tests the neocloud playbook with $40 billion in planned spending

Nebius used its third-quarter earnings call on Thursday to outline $40 billion in planned spending for 2027, a figure well above what Wall Street had anticipated. The company intends to pay for the buildout through customer prepayments and loans secured by customer contracts, in effect borrowing against the future value of the data centers it is constructing. CEO Arkady Volozh acknowledged the difficulty directly on the call, saying that building at this scale is hard and that delays are part of the industry right now, adding that the company is not immune.
The plan already rests on projects showing strain. Microsoft, one of Nebius's largest customers, is paying for AI capacity at a Vineland, New Jersey data center that is now months behind schedule. The Microsoft contract is worth up to $19.4 billion, but deadlines are slipping: only just over half of that capacity is now planned for delivery by the end of the year, with the remainder pushed to the second quarter of 2027. The original tranches were meant to be deployed in 2025 and 2026, so a Q2 2027 date sits well past the contracted window.
The cause, as described by chief product and infrastructure officer Andrey Korolenko, was that DataOne, the third-party operator of the site, wound down temporary generation faster than expected as the facility switches to Bloom Energy fuel cells. That transition was not entirely voluntary. In August the investigative outlet Floodlight identified at least 45 natural gas generators running at the DataOne site without permits, and New Jersey regulators fined the facility $1.1 million, finding the generators' use violated federal law. DataOne also faces a noise-complaint lawsuit from nearby residents over an alleged constant humming from the data center.
Under Nebius's own summary of the Microsoft contract, Microsoft can terminate affected service after a grace period if dates are missed and no alternative capacity is offered, and the agreement carries financial penalties for late delivery. Nebius said Microsoft has been part of the planning process but did not say whether Microsoft has agreed to the new dates; Microsoft has not publicly canceled anything.
The timing is awkward because Microsoft appears to be re-examining its neocloud relationships. Reports indicate Microsoft is cooling on neocloud deals that miss deadlines and is tightening oversight of third-party-run projects, including those involving Nebius, IREN and Nscale, while debating whether to sign new agreements. Bloomberg reported that Microsoft sent employees to the New Jersey site, declined an option that would have more than doubled its Nscale agreement for a Texas data center, and recently stopped being an anchor customer for Nscale's planned Essex site after power delays. In its own quarterly report, Microsoft attributed capital spending below expectations to third-party delays.
Nebius frames the problem as external. It says the delays come from sites it does not control, while data centers it builds itself are arriving on time or ahead of schedule, and those will supply most of its new capacity from 2027. Chief revenue officer Marc Boroditsky said deals signed with Microsoft and Meta both included substantial prepayments that arrived long before delivery, and that new agreements signed in the third quarter came with prepayments more than covering the cost of the capacity behind them. The company ended the quarter with $7.4 billion in cash.
The financing math is the crux. Nebius expects prepayments plus asset-backed financing of investment-grade contracts to cover up to 85% of a 2027 capital expenditure range of $40 billion to $45 billion. CFO Maria Del Dado Alonso Sanchez identified the Microsoft and Meta contracts as ones that can be financed this way, and Boroditsky said the company could draw on prepayments to shore up any additional cash needs. Nebius forecast 2027 revenue of $12 billion to $13 billion and said it expects to break even on a pre-tax basis by the fourth quarter.
For the most recent quarter, Nebius reported revenue of $981 million, up 571% year over year, though roughly a third of that was a one-time payment tied to a new partnership model. The company cut its 2026 revenue forecast by $200 million to $3 billion, citing delays at third-party sites such as the one in New Jersey. Shares closed the day down 17%.
In practice, the model Nebius describes is a form of contract-backed project finance. A neocloud is a GPU and AI infrastructure provider that rents capacity to model developers and hyperscalers rather than owning the whole stack itself; the name distinguishes it from the large cloud platforms. Lenders who advance money against a signed contract are underwriting the counterparty and the delivery schedule as much as the hardware. That works when capacity arrives on time, because revenue begins while debt service is still small. It gets harder when a site slips: costs keep accruing, revenue shifts to the right, and the lender's collateral, the contract itself, becomes less certain if the customer gains a right to walk away. This suggests the risk in Nebius's plan is less about demand for compute than about execution at facilities it does not operate. The prepayment cushion is real and the cash balance is substantial, but a large share of the 2027 build depends on third parties meeting dates.
A likely trade-off is control. Building owned sites on schedule reduces dependence on operators like DataOne, but it also consumes capital earlier and concentrates schedule risk internally. Nebius says self-built capacity will be the bulk of new supply from 2027, which fits that logic.
Why it matters: Developers and product teams buying capacity from neoclouds should treat delivery dates as softer than headline contract values suggest, since a multibillion-dollar agreement with a hyperscaler can slip by more than a year when a subcontractor's power plan changes. Inference capacity planning that leans on a single provider or region carries schedule risk that may not show up in published contract totals. The episode is also a reminder that the AI buildout's binding constraint is increasingly power, permitting and site operations rather than chips, which is where procurement timelines and pricing pressure are likely to shift next.